Construction of New Gas Insulated Substation 110kV, Unipetrol RPA, Area of Záluží

Detail of HV 110kV switchboard installation, control cabling

Detail of HV 110kV switchboard installation, control cabling
12.5.2021

Installation of protection relay cabinets

Installation of protection relay cabinets
14.4.2021

Performance: 1.1.2020 – 04/2022
Substation 110kV – 27 switchgear bays
Control cabinets including protection – 27 pieces
Complete construction of switchgears of unit auxiliaries
Back-up battery power supply including inverters
Adjustments of protection in powered units PCH, R200, R700, RAP
Complete air-conditioning and heating system of the new substation and unit auxiliaries including battery unit
Complete lighting of the new substation and unit auxiliaries
Construction of new routes for VHV and LV cabling including VHV and LV cables
Installation of terminals and VHV connections
Building of GIS and auxiliary units
By-pass of existing networks
 

Installation of VHV metal-enclosed switchgear

Installation of VHV metal-enclosed switchgear
26.3.2021

First supplies of VHV ABB GIS

First supplies of VHV ABB GIS
11.3.2021

Construction of steel structures and jacketing

Construction of steel structures and jacketing
7.1.2021

Foundation concreting

Foundation concreting
16.11.2020

 

INELSEV s.r.o.

Husitská 1716
434 01 Most
Email: info@inelsev.cz
 
Phone: +420 474 721 602

ID: 25001582
Tax ID: CZ25001582
Data Box ID: 3t8bw6z

INELSEV s.r.o. branch office Most

Dělnická 34
434 01 Most - Velebudice
Email: info@inelsev.cz
 
Phone: +420 474 721 602
Terms of Use | Privacy Policy
Copyrights © 2024 Inelsev