ORLEN UNIPETROL RPA s.r.o. |
Backup power supply of the fire station st. 2705 |
2021-2022 |
Petrochemicals |
Processing of documentation for a building permit, processing of implementation documentation, complete construction of a new substation including internal equipment, grounding and lightning conductor. Design and supply of a backup system (UPS + motor generator), supply and installation of LV switchboards, supply and installation of air handling and air conditioning. |
ORLEN UNIPETROL RPA s.r.o. |
Reconstruction of LV switchboards at construction site 1613 |
2021-2022 |
Petrochemicals |
Processing implementation project documentation, complete disconnection of states. cables and dismantling of 30 fields of LV switchboards, supply of new modular and cabinet switchboards incl. installation and rewiring of all cables. Supply and installation of air conditioning and air conditioning in the substation. Installation of entrance and attendance system. Settings of UMC modules, protection. Individual and comprehensive testing and tests of approx. 80 el. engines. |
T.EN Netherlands BV |
New furnace BA111 - ESD HIMA |
2021-2023 |
Petrochemicals |
Processing of ESD HIMA implementation project documentation for new furnace No. 11, complete supply of HW and SW, supply and installation of cables, connection and testing. Delivery and installation of a new matrix panel in the control room, including its testing. |
T.EN Netherlands BV |
New oven BA111 |
2021-2023 |
Petrochemicals |
Processing OSBL implementation documentation, partial delivery of E&I material, E&I assembly work, tests and assistance when starting a new unit |
KOVOŠROT GROUP CZ s.r.o. |
Delivery and installation of LV switchboards |
2022 |
Ecology and Recycling |
Monitoring of the current state of installations, implementation documentation for the production of LV switchboards, supply of switchboards and assembly itself, tests. |
ORLEN Service s.r.o. |
Installation of AUMA electric drives, R-3001R-3002 |
2022 |
Petrochemicals |
Processing E&I implementation project documentation, delivery of AUMA drives, installation of E&I equipment, tests |
CHEMINVEST s.r.o. |
Expansion of warehouse forces for PP |
2021-2022 |
Petrochemicals |
Processing E&I implementation design documentation, delivery and assembly of E&I, EPS, construction site equipment |
UNIPETROL RPA s.r.o. |
Combustion Optimization - CCR Furnace |
2022 |
Chemistry |
Development of the MaR implementation project, delivery of instrumentation, assembly, testing, commissioning. |
SYNTHOMER as |
Automatic propylene bottling |
2021-2023 |
Chemistry |
Elaboration of implementation projects of technology, electrical, MaR, mechanical, mechanical. Delivery of winding arms, compressors, ŘS, MaR and electrical switchboards, frequency converters, MaR devices, cable connection. Assembly work, individual and complex tests, commissioning. |
SYNTHOMER as |
MAA storage |
2022 |
Chemistry |
Elaboration of implementation projects of technology, electrical, MaR, mechanical, mechanical. Delivery of pumps, ŘS Yokogawa, switchboards, MaR devices, cable connection. Assembly work, individual and complex tests, commissioning. |
HABRINOL Děčín s.r.o. |
Measuring Toluene and Xylene Levels |
2022 |
Chemistry |
Development of the MaR implementation project, delivery of instrumentation, assembly, testing, commissioning. |
UNIPETROL RPA s.r.o. |
Optical connections of the Chempark complex |
2022 |
Chemistry |
Development of implementation projects of optical connections, supply of complete optical components, assembly, welding of optical fibers, measurements, tests, commissioning. |
UNIPETROL RPA s.r.o. |
Chezacarb - New cooling unit |
2021-2023 |
Chemistry |
Elaboration of electrical, MaR, mechanical implementation projects. Delivery of a new cooling unit, assembly, testing, commissioning. |
UNIPETROL RPA s.r.o. |
NDB line relocation from PIB |
2021-2023 |
Chemistry |
Elaboration of implementation projects of electricity, MaR, HVAC, EPS, NO. Delivery and assembly, tests, commissioning. |
UNIPETROL RPA s.r.o. |
LR 2002 - replacement of 6 kV motors |
2021-2023 |
Refineries |
Elaboration of electrical, MaR, mechanical, mechanical implementation projects. Delivery of 6kV motors, conversion of HV switchgear, cable connection. Assembly work, individual comprehensive tests, commissioning. |
UNIPETROL RPA s.r.o. |
New DCPD Production Unit |
2021-2022 |
Chemistry |
Elaboration of implementation projects of electricity, weak currents, EPS, GDS. Deliveries, assembly, comprehensive tests, commissioning. |
UNIPETROL RPA s.r.o. |
LS 18038 - waste water management on the territory of the refueling station |
2021-2022 |
Refineries |
Elaboration of electrical implementation projects, MaR. Assembly work, individual and complex tests, commissioning. |
ČEZ Energo, s.r.o. |
KGJ Procurement |
2022 |
Energy |
Delivery and installation of the electrical part, including output to the HV network during the installation of a new cogeneration unit in the Zákupy gas boiler house |
MERO CR as |
Replacement of flowmeters and density meter for CTR |
2022 |
Chemistry and petrochemicals |
Ensuring a complete replacement of DN300 ultrasonic flowmeters for oil flow measurement at the Central Tank Station, including replacement of the oil density meter |
MONDI Štětí, as |
Upgrade of regeneration boiler RK12 |
2022 |
Paperwork |
Delivery and installation of electrical parts for the new combustion air supply technology to the regeneration boiler |
Lovochemie as |
Optical and power distribution cables |
2022 |
Chemistry and petrochemicals |
Switching of electrical and optical power supply lines during the liquidation of the NPK production unit for surrounding technologies while maintaining their full operation |
Synthesia, as |
Reconstruction of substation RSS 1 |
2021 - 2022 |
Chemistry and petrochemicals |
Processing of project documentation and implementation of a complete replacement of LV substation equipment, cable distributions and construction modifications and new substation electrical installation. |
Ministry of Defense of the Czech Republic |
Prostějov environmental heating |
2021 - 2022 |
Energy |
Project documentation and implementation of the electrical part during the modernization of the area's heating system and the construction of a storage and biomass boiler |
PREOL, as |
Extraction Recovery |
2021 - 2022 |
Chemistry and petrochemicals |
Disassembly and assembly work during the restoration of construction and technological wiring after the accident of the production unit of extraction |
"The heating plant České Budějovice, as" |
Substation control system addition 1.1 |
2021 |
Energy |
Realization project documentation, including documentation of the actual execution. Delivery of the control panel, installation of new cable routes with the laying of new power and control cables. SW work at ØS EMERSON for control and signaling of the 6kV substation, including connection to superstructure systems. |
MERO CR, as |
Installation of electricity connection points |
2021 |
Chemistry and petrochemicals |
Supply and installation of switchboards as electrical power connection points for service activities in the area of the central oil tank in Nelahozevs. |
Airport Prague, as |
Aviation Fuel Station |
2020 -2021 |
Other |
Modernization of control and management of aviation fuel bottling technology including replacement of switchboards with frequency converters and new pump motors in an Ex environment. |
MONDI Štětí, as |
Project PM1 EcoVantage |
2020 - 2021 |
Paperwork |
The complete reconstruction and modernization of the paper machine (PM1) included the development of project documentation in the MaR and electrical professions, the production of LV and DCS switchboards in the number of approximately 150 fields. The actual disassembly and assembly work took place during the PM1 shutdown in parallel with all professions on the construction site |
Airport Prague, as |
Paint and drying box |
2020 - 2021 |
Other |
Supply and installation of air conditioning control including a hazardous gas detection system for a new painting operation. |
ČEZ Distribuce, as |
TR Beroun - transformer station renovation (IE-12-6004102) |
2019-2021 |
Energy |
Realization of the construction "TR Beroun - renovation of the 110/22 kV transformer house" construction no. IE-12-6004102, PS10 - Switchboard 22 kV, PS30.4 - Optical network, PS66 - Station optical cable, SO340 - external lighting, SO521.1 - Covered substation LV. |
"VRŠANSKÁ UHELNÁ as Location Hrabák; CR" |
"Modernization of long-distance passport transport width 1200 using frequency converters" |
2021 |
Energy |
Reconstruction of long-distance belt transport in the scope of a complete replacement (delivery, assembly, revision, revival and commissioning) of power and control distributions including HV switchboards, field instrumentation including the control system of PD157 belt conveyors and PD158. Part of the contract was implementation project documentation and documentation of the actual state. |
ČEZ Teplárenská, as |
Reconstruction of the 6kV substation VTK |
2021 |
Energy |
Reconstruction of the existing dungeon substation 6.3kV R6-VTK, dual system in the scope of complete replacement (delivery, installation, revision, revival and commissioning) of power and control distribution of dungeon No. 01 -12. replacement of disconnectors, switches, measuring transformers and buses, including control switchboards and protections. Part of the contract was implementation project documentation and documentation of the actual state incl. KKS certification. |
"Coal Services as V. Řezáče 315, 434 67 Most" |
PD - TR Hrabák Protection Replacement |
2021 |
Energy |
Exchange of protections, project documentation |
ČEZ Distribuce, as |
"REA_VR_IE-12-4004670 LN_Hřivice, sm. Konětopy, reconstruction of NN, II. stage" |
2020 |
Energy |
Reconstruction of the LV network, cabling of the municipality, II. Stage |
ČEZ Distribuce, as |
"REA_VR_IE-12-4004699 MO_Most, Prok, Diviše, postal code 2597 LV cabling" |
2021 |
Energy |
Reconstruction of the LV network, cabling of Prokop Diviše street, Most |
ČEZ Distribuce, as |
"REA_VR_IV-12-4018619 LT-Mrsklesy, No. 15, 30, 48 strengthening kNN" |
2021 |
Energy |
Reconstruction of the LV network, cabling |
ČEZ Distribuce, as |
"REA_VR_IE-12-4005885 TP-Háj u Duchcova - LV cabling, III. stage" |
2021 |
Energy |
Reconstruction of the LV network, cabling of the village, III. Stage |
ČEZ Distribuce, as |
"REA_VR_IE-12-4006133 CV_High - LV cabling" |
2021 |
Energy |
Reconstruction of the LV network, village cabling |
ČEZ Distribuce, as |
"REA_VR_IE-12-4004303 LN_Velká Černoc, cab. NN, pp. 1410/17, I. stage" |
2021 |
Energy |
Reconstruction of the LV network, village cabling, I. stage |
ČEZ Distribuce, as |
"REA_VR_IV-12-4017513 TP_Dubí, Lidica garden colony" |
2021 |
Energy |
"Connection of new OM - construction of a new compact substation 1x630 kVA, transformer 400 kVA. Divorces of NN after the gardening colony." |
ČEZ Distribuce, as |
"REA_VR_IE-12-4006049 TP_Jeníkov-Oldřichov dokoč. cabling" |
2021 |
Energy |
Reconstruction of the LV network, completion of village cabling |
ČEZ Distribuce, as |
"REA_HZS_OE-12-4002144 CV_V-Jirkov-Boleboř-Rudoltice 173-189, MKPB" |
2021 |
Energy |
Reconstruction of the LV network, village cabling |
ČEZ Distribuce, as |
"REA_VR_IV-12-4018565 CV_Miřetice u Klášterce - LOCATION 26 RD" |
2021 |
Energy |
"Modification of the distribution system (DS) by expanding it - building a new distribution substation (DTS). LV cables of type AYKY 3x240+120 are brought out of the new DTS, which connect (loop) the location of 26 new family houses. SS200 and SS100 enclosures are used for connection." |
ČEZ Distribuce, as |
"REA_VR_IE-12-4005920 LN_Bílenec - reconstruction of vol. NN" |
2021 |
Energy |
Reconstruction of the LV network, village cabling, I. stage |
Petersburg municipality |
Public lighting Bílenec |
2021 |
Municipality |
Reconstruction of public lighting in the village of Bílenec. |
ČEZ Distribuce, as |
"REA_HZS_IV-12-4019257 CV_Vrskmaň,Unisteel,TS,kVN,kNN" |
2021 |
Energy |
New HV, LV cable lines and a new HV/LV distribution substation in the village of Vrskmaň. TS is located on the plot parc. no. 574/16 in c.ú. Kyjice. |
Měcholupa Township |
Public lighting Velká Černoc |
2021 |
Municipality |
Reconstruction of public lighting in the village of Velká Černoc. |
CHEMINVEST s.r.o. |
Hydrogen Sulfide Risk Elimination in External and Primary Gasoline |
2020 - 2021 |
Chemistry |
Processing of project documentation for electrical, MaR, GDS parts. Controlling the bottling of petrol containing hydrogen sulphide on railways. PLC connection and configuration including SW modification in DCS, supply and installation of GDS system including its modifications, supply of cables and cable routes, addition of switchboards, power supply |
BIS Euromont as |
Production of HVO at PS 2304 - Mixing tanks |
2020 - 2021 |
Chemistry |
Processing project documentation for electrical parts, MaR. Connection to the Foxboro system, supply of cables and cable routes, modifications in the connection and addition of LV switchboards, production of power supply, temperature control and mixing in HVO tanks |
ORLEN UNIPETROL RPA s.r.o. |
Fire water management at the Jiřetín gas station |
2020 - 2021 |
Chemistry |
Processing of project documentation for electrical, MaR, mechanical, construction parts. Supply and installation of cable routes, cables. HW and SW deliveries and configuration and connection to the DeltaV system (EMERSON). Adjustments in the connection of LV switchboards incl. making a power supply. Supply and installation of dampers with AUMA drives incl. accessories |
ČEPRO as |
Reconstruction of 6kV compensation, Nové Město warehouse |
2021 |
Chemistry |
Processing ELEKTRO project documentation, supply and installation of cable routes, supply and installation of LV and HV cables, supply and installation of new compensating switchboards. Adjustments in the connection of HV switchboards. |
ORLEN UNIPETROL RPA s.r.o. |
CHC revitalization - New GB1 and GB2 UPS at CHC |
2021 |
Chemistry |
Processing ELEKTRO project documentation, supply and installation of cable routes, supply and installation of cables, supply and installation of new parallel UPS. Adjustments in the connection of LV switchboards. Connection to the DP AGRO supervisory workplace, including the installation of optical interconnection of buildings and complete commissioning of the system. |
ORLEN UNIPETROL RPA s.r.o. |
Reconstruction of the switchboard MRS1 + MRS11 incl. UPS and motor generator |
2021 |
Chemistry |
Processing of ELEKTRO project documentation, supply and installation of cable routes, LV cables, supply and installation of an uninterruptible power supply system. energy, i.e. supply and installation of a CAT motor-generator with an output of 300 kVA, supply of 2 pcs of parallel UPS with an output of 80 kVA. Construction modifications of the engine room for the installation of MTG construction penetrations under the switchgear. Delivery and installation of new LV switchboards, transformers. Connection to the DP PCH supervisory workplace. Individual and comprehensive testing |
SYNTHOMER as |
Elaboration of a HAZOP study |
2020 - 2021 |
Chemistry |
Elaboration of a HAZOP study for a new gas boiler house |
SYNTHOMER as |
Adjustment of heating line no. 6 |
2020 - 2021 |
Chemistry |
Processing of ELEKTRO, MaR, ŘS, construction and mechanical project documentation. Supply and installation of material and equipment, especially pumps, pipelines, valves, field instrumentation and cable routes, cables. Construction work, construction assistance. Mechanical work, pipeline installation, pump installation and commissioning. Individual and comprehensive testing. Commissioning. |
BERTSCH ENERGY GmbH |
New power supply for GA 1201 R.1 and R.2 electric waterer |
2019 - 2021 |
Chemistry |
Processing ELEKTRO project documentation, supply and installation of cable routes, HV cables. Adjustments in the connection of HV switchgear incl. LV setup incl. modifications and readjustment of protections. Construction and excavation work. Connection to the supervisory workplace of DP PCH. Individual and comprehensive testing |
BERTSCH ENERGY GmbH |
New HV inlets for the construction of a new boiler house at EJ, UNIPETROL RPA campus |
2019 - 2021 |
Chemistry |
Processing ELEKTRO project documentation, supply and installation of cable routes, HV cables. Adjustments in the connection of HV switchgear incl. LV setup incl. adjustments and readjustment of protections. Construction and excavation work. Connection to the supervisory workplace of DP PCH. Individual and comprehensive testing |
ČEPRO as |
Reconstruction of switchboard item 102 |
2020 |
Chemistry |
Processing ELEKTRO project documentation, construction and excavation work, supply and installation of LV cables. Supply and installation of LV switchboards. Delivery and installation of street lighting. Individual and comprehensive testing |
UNIPETROL RPA s.r.o. |
COMBUSTIONONE system installation for furnaces BA-108, 109 AND 110 NA EJ |
2020 |
Chemistry |
Processing of project documentation, delivery and implementation for the installation of the combustion optimization system, including the delivery of switchboards, cabling, local control boxes and connection of cable routes. New MaR switchboard and electrical. |
UNIPETROL RPA s.r.o. |
Deployment of the Delta V control system at the water plant 230 |
2020 |
Chemistry |
Processing of project documentation, delivery and implementation for the replacement of the existing control system, including the replacement of the switchboard, cabling, local control boxes and connection of cable routes. New MaR switchboard, UPS systems, optical connection and termination of communication with other primary carriers. |
UNIPETROL RPA s.r.o. |
Automation of gas burners K19 on T700 |
2020 |
Chemistry |
Processing of project documentation, delivery and implementation for the replacement of the existing automatic burners, for the K19 boiler, including the replacement of the switchboard, cabling, local control boxes and connection of cable routes. New MaR switchboard, fitted with Siemens SIMATIC S7-1500 PLC system. |
UNIPETROL RPA s.r.o. |
Acid Water Striper |
2018-2019 |
Chemistry |
Processing of high current project documentation, measurement and regulation of EPS, GDS. Construction of a new LV substation, supply of switchboards, cable routes, cabling, lighting including NO with CBS switchboard. Carrying out individual tests, commissioning, revision. Processing of MaR and ŘS project documentation, supply and installation of field instrumentation, supply and installation of cabling and cable routes, supply of HW and SW for Foxboro ŘS, supply and installation of GDS, EPS |
UNIPETROL RPA s.r.o. |
Automatic failure of switchboards on NRL operation |
2019-2020 |
Chemistry |
Processing of project documentation, arming of HV, LV switchgear, cable connection of individual switchgear. Carrying out individual tests, commissioning, revision. |
UNIPETROL RPA s.r.o. |
Establishment of a supervisory workplace on the territory of the Refinery |
2019-2021 |
Chemistry |
Processing of project documentation, delivery of new switchboards, optical connection. Creation of a new system for the supervisory workplace. Carrying out individual tests, commissioning, revision. |
UNIPETROL RPA s.r.o. |
Electric heating of the new oily water pipeline |
2019-2020 |
Chemistry |
Processing of project documentation and realization of measurement and regulation part, high current. Supply and installation of new heating switchboards, flow meter, el. heating, DCS adjustment. Carrying out individual tests, commissioning, revision. |
UNIPETROL RPA s.r.o. |
TSB Tank Reconstruction |
2019-2020 |
Chemistry |
Processing of the power project and MaR. Complete deliveries and assembly for grounding, lighting of the new tank, measurement. Conducting tests, commissioning, revision |
CB&I Ltd |
NHCU Rehabilitation 3rd phase |
2020 |
Chemistry |
Delivery and installation of LV switchboards, modification of HV switchboards R6.1 and R6.2 Delivery and installation of field instrumentation including setting and recovery, delivery and installation of electric and steam heating |
Union Lesní brána as |
RTX bath power supply |
2020 |
Chemistry |
Development of project documentation, supply and installation of 10kV HV switchboard, transformer and LV switchboards, cable connection including routes. Setup and Commissioning. |
UNIPETROL RPA s.r.o. |
MNSiS switchboard replacement at water plant 02 |
2020 |
Chemistry |
Development of project documentation, delivery and installation of a new LV switchboard including commissioning. Dismantling and disposal of the old LV switchboard. |
UNIPETROL RPA s.r.o. |
Kralupy - KR20014_ switchboard TR8616_B |
2020 |
Chemistry |
Development of project documentation, supply and installation of a new HV 6kV switchgear including connection and commissioning. |
ABB s.r.o./ UNIPETROL RPA s.r.o. |
Retrofit of HV fields on T 700 |
2020 |
Chemistry |
Delivery and installation of LV superstructures for HV switchgears RWA1 and RWD1, including replacement of measuring transformers, modification of HV fields and cable connection. |
HABRINOL DĚČÍN s.r.o. |
Development of a HAZOP study |
2020 |
Chemistry |
Elaboration of a HAZOP study. |
HÜTTENES ALBERTUS CZ s.r.o. |
Air Route Fix |
2020 |
Chemistry |
Processing of project documentation and implementation of the measurement and regulation part, supply of devices, switchboards, cables and cable routes |
UNIPETROL RPA s.r.o. |
Reconstruction of part of the MaR facility - Ammonia |
2020 |
Chemistry |
Processing of project documentation and implementation of the measurement and regulation part, supply of devices, switchboards, cables and cable routes |
Icopal Vedag s.r.o. |
Reconstruction of the boiler room |
2020 |
Chemistry |
Processing of project documentation and implementation of measurement and regulation and electrical parts. |
UNIPETROL RPA s.r.o. |
Kralupy - KR19018_ switchboard TR8616_A |
2019 |
Chemistry |
Development of project documentation, supply and installation of a new HV 6kV switchgear including connection and commissioning. |
ABB s.r.o./ UNIPETROL RPA s.r.o. |
Retrofit of HV fields on T 700 |
2019 |
Chemistry |
Delivery and installation of LV superstructures for HV switchboards RWB1 and RWC1, including replacement of measuring transformers, modification of HV fields and cable connection. |
UNIPETROL RPA s.r.o. |
Reconstruction of lighting at the waterworks |
2019 |
Chemistry |
Processing a technical proposal for the replacement of existing lighting, processing implementation project documentation. Dismantling work of existing lighting and installation of new lighting. The regulation of the lamps was designed using the DALI bus, where the lamps themselves are regulated by daylight. |
HABRINOL DĚČÍN s.r.o. |
New product trays |
2019 |
Chemistry |
Elaboration of project documentation, supply and installation of an electro-pneumatic terminal with ProfiBus communication. Supply and installation of cable routes and signaling and control cables. Delivery and installation of new junction boxes. |
Synthos Kralupy |
Temperature regulation in H72ab and H74b reservoirs |
2018 |
Chemistry |
Processing of project documentation and implementation of the part of measurement and regulation, high current and machine modifications during the restoration of automatic temperature control in storage tanks |
Synthos Kralupy |
Distillation of Butadiene |
2018 |
Chemistry |
Implementation of the electrical and measurement and regulation part during the construction of a new Butadiene Distillation unit, for the purification of incoming Butadiene |
ČEPRO as |
New LV cabinet switchboard in substation 256 |
2018 |
Refineries |
Part of the work was the replacement of the existing LV switchboard with 7 fields for a new one with the same electric. equipment including disconnection and reconnection of all cables. Individual and comprehensive testing |
UNIPETROL RPA s.r.o. |
Reconstruction of the lighting of building 1614 (Chezacarb warehouse) |
2018 |
Chemistry |
The subject of the implementation was the complete replacement of 120 pieces of existing lighting in the storage hall with new LED lights, including complete cable routes and cabling. It also included individual and comprehensive testing. |
UNIPETROL RPA s.r.o. |
Ammonia lighting reconstruction - engine room (LED) |
2018 |
Chemistry |
The subject of the implementation was the complete replacement of 135 pieces of existing engine room lighting with new LED lamps designed for Ex environments, including complete cable routes and cabling. It also included individual and comprehensive testing. |
UNIPETROL RPA s.r.o. |
Reconstruction of switchboard and electrical distribution for E-903A exchanger |
2018 |
Chemistry |
The subject of the implementation was the replacement of the existing pressure switchboard in the Ex area with a new one, including the adjustment of the air connection point and the construction of a new power supply, i.e. the installation of a new power cable. Part of the switchboard was the delivery of a control unit for controlling the draft and keeping the switchboard under constant pressure. Construction and excavation work. Individual and comprehensive testing |
UNIPETROL RPA s.r.o. |
Revitalization of fire stations st. 2705 and st. 7202 |
2018 |
Chemistry |
The work consisted in the implementation according to the presented project documentation, where the complete lighting in the premises of the fire stations of building 2705 and building 7202 was replaced. LED lights were designed and installed in the raster soffit. Another part of the revitalization was the installation of 23 indoor air conditioning units, including the installation of all accessories |
ABB s.r.o. |
Intelligent Petrochemical Power Supply System |
2017-2018 |
Chemistry |
Processing implementation project documentation. The implementation consisted in the replacement of 32 ABB terminals, including internal wiring in the LV superstructure. Connecting new terminals to MiroScada RS. Creation of a new autonomous SW at the supervisory workplace for the control of load disconnection in the event of an overload signal of the HV power transformers. Individual and comprehensive testing. |
ČEPRO as |
Reconstruction of hydrant network, Čepro, warehouse Loukov |
2018 |
Chemistry |
Implementation of the MaR, electrical and ASŘTP part |
UNIPETROL RPA s.r.o. |
POX revitalization - electric motors for POX |
2018 |
Chemistry |
Processing of project documentation and implementation of the part of measurement and regulation and machine adjustments. |
HABRINOL DĚČÍN s.r.o. |
Measurement of switchboards by thermal imaging technique |
2018 |
Chemistry |
Measurement of switchboards by thermal imaging technique |
HABRINOL DĚČÍN s.r.o. |
Filling and storage area of IBC containers, bottling to AC |
2018 |
Chemistry |
Processing of project documentation and implementation of the part of measurement and regulation and machine adjustments. |
UNIPETROL RPA s.r.o. |
Installation of new MaR equipment at the ČP-DSČ production plant |
2018 |
Chemistry |
Processing of project documentation and implementation of measurement and regulation and machine adjustments. |
UNIPETROL RPA s.r.o. |
Replacement of control fittings for lowering steam curtains |
2018 |
Chemistry |
Processing of project documentation and implementation of the part of measurement and regulation and machine adjustments. |
UNIPETROL RPA |
Installing a new safety valve on column DA-701 |
2018 |
Chemistry |
Processing of project documentation, delivery of valves and implementation. Connection of new measurements to the ABB control system, execution of tests and revisions. |
Synthos Kralupa |
DKE Flow Measurement - Ethylbenzene II |
2018 |
Chemistry |
Processing of project documentation, flow meter delivery and implementation. Connection of new measurements to the Delte-V control system, execution of tests and revisions. |
Synthos Kralupa |
Nitrogen connection of the EB pipeline |
2018 |
Chemistry |
Processing of project documentation, delivery of devices and implementation. Connecting new measurements to the Foxboro control system, performing tests and revisions. |
UNIPETROL RPA s.r.o. |
Automation of K14 washers and blowers on T700 |
2018 |
Chemistry |
Processing of project documentation, delivery and implementation for the replacement of the existing automation of swinging, long-extending blowers and rotary sprinklers (OF-OS) for the K16 boiler, including the replacement of the switchboard, cabling, local controls cabinets and connection of cable routes. New MaR switchboard, fitted with Siemens SIMATIC S7-1500 PLC system. |
UNIPETROL RPA s.r.o. |
Automation of K19 washers and blowers on T700 |
2018 |
Chemistry |
Processing of project documentation, delivery and implementation for the replacement of the existing automation of swinging, long-extending blowers and rotary sprinklers (OF-OS) for the K16 boiler, including the replacement of the switchboard, cabling, local controls cabinets and connection of cable routes. New MaR switchboard, fitted with Siemens SIMATIC S7-1500 PLC system. |
SANDVIK |
Ro1-104 cabinet replacement |
2018 |
Other |
Processing of project documentation and implementation of the replacement of the faulty switchboard, carrying out individual tests, commissioning, revision. |
PROFOL Czech s.r.o. |
New storage hall |
2018-2019 |
Other |
Processing of high current + heating projects using e. SAHAR. Complete supply and assembly of LV switchboards, cable routes, cables, lighting, settings, testing, commissioning, revision |
UNIPETROL RPA s.r.o. |
Simultaneous adjustable injection of lubricant products from tank C to K56 |
2018-2019 |
Refinery |
Processing of project documentation and implementation of measurement and regulation, power and machine parts. Delivery and installation of a new RD switchboard for connecting new flow meters. In the measurement section, supply and installation of flowmeters, valves, DCS adjustment. In the machine part, disassembly of pipelines and supply and installation of new pipelines. Carrying out individual tests, commissioning, revision. |
UNIPETROL RPA s.r.o. |
Injection of additives into the VFCR stream |
2018-2019 |
Refinery |
Processing of electrical and MaR implementation documentation, supply assurance, modification of LV switchboards, delivery of new LV switchboards, el. heating, cable routes, cable distribution. In the MaR section, supply of field instrumentation devices for connection to the existing ŘS. Carrying out individual tests, commissioning, revision. |
UNIPETROL RPA s.r.o. |
Tank Exchange 5710 - E18 |
2018 |
Refineries |
Processing the power project. Complete supplies and installations for grounding, lighting of the new tank 5710-E18. Conducting tests, commissioning, revision |
CHEMINVEST s.r.o. |
PS20 - Capacitance of sump 7609 |
2018 - 2019 |
Chemistry |
Supply and installation of new switchboards, cables and routes. Arming of existing switchboards. Supply and installation of field instrumentation devices. Connection of technology to the RS. Setup, testing and commissioning of equipment. |
CHEMINVEST s.r.o. |
Fire Integrity Route 7521 - ISBL |
2018 |
Chemistry |
Delivery and installation of the kiosk including the emergency lighting control panel, air conditioning and complete implementation and commissioning. |
AIR PRODUCTS |
Compensation Installation R10.1/19 |
2018 |
Chemistry |
Assembly and connection of the compensating switchboard including modifications of the HV field. |
ABB s.r.o./ UNIPETROL RPA s.r.o. |
Retrofit of HV fields on T 700 |
2018 |
Chemistry |
Delivery and installation of LV superstructures for HV switchboards RWB2 and RWC2, including replacement of measuring transformers, modification of HV fields and cable connection. |
Net4Gas |
Modernization and expansion of KS HSKA capacity |
2019 |
Gas industry |
Processing of project documentation and implementation of deliveries and works for expanding the capacity of the border gas transfer station to Germany |
Bayernoil, Germany |
Reconstruction of refinery operations |
2019 |
Chemistry |
Performance of electrical and instrumentation assembly work during the reconstruction of operating sets at the refinery in Vohburg (Germany) |
Constellium Děčín |
Production halls No. 32, 33, 34 |
2019 |
Construction |
Supply and installation of a part of the MaR and spatial detection of gas during the construction of the three new production units |
Slovnaft as |
MC/CC4-MOC788 blinds CHV1-20 |
2018 |
Chemistry |
Elaboration of project documentation for the grounding of the structure of the blinds and the repair of downspouts on cooling towers IV. |
Slovnaft as |
Replacement of air conditioning equipment in the Slovnaft complex |
2018 |
Chemistry |
Replacement of air conditioning equipment in the Slovnaft complex (Bratislava), operations P2, P3, P4, P5, P7, P82. |
Slovnaft as |
"LOG/MC18/144/ZVHH/CA/Installation of ultrasonic flowmeters for filling arms in order 360 " |
2018 |
Chemistry |
Installation of ultrasonic flowmeters on filling arms in ŽC. Terminal Horný Hričov |
Slovnaft as |
Replacement of air conditioning equipment in the Slovnaft complex |
2018 |
Chemistry |
Replacement of air conditioning equipment in the Slovnaft complex (Bratislava), operations P2, P3, P4, P5, P7, P82. |
Slovnaft as |
Reconstruction of lateral filtration on CC1 |
2018 |
Chemistry |
Development of an implementation project for the reconstruction and replacement of sand filtration fittings at the CC1 circulation center |
Slovnaft as |
MOC15_490_FCC_RPD_Protection of KSB pumps |
2018 |
Chemistry |
"More reliable operation and increased degree of protection of pumps 15P101AB, 15P103AB, 15P111AB will be secured by sensing pump flooding by installing a level sensor on the suction side. " |
Slovnaft as |
MC17_BRRED_1198_Development of RPD - Addition of lighting for service platforms on VJ RR |
2018 |
Chemistry |
Elaboration of project documentation for the lighting of three platforms on the hydrogen unit. |
Slovnaft as |
LOG_MC18_227_PČ_CA_Installation of emergency stop valve |
2018 |
Chemistry |
Installation of the emergency stop valve in the Bratislava port terminal. |
Slovnaft as |
|
2018 |
Chemistry |
Elaboration of project documentation for draining condensate from pipelines. |
Slovnaft as |
MOC15_BFCCU_654_Installation of KZ in RNN6601 |
2018 |
Chemistry |
Elaboration of project documentation for the addition of cooling in the RNN6601 substation. |
Slovnaft as |
MOC15_BHPP1_652_Installation of KZ in RVN5603 |
2018 |
Chemistry |
Elaboration of project documentation for the addition of cooling in the substation RNN5603. |
Slovnaft as |
MOC15_BVDU5_653_Installation of KZ in RVN5602 |
2018 |
Chemistry |
Elaboration of project documentation for the addition of cooling in the RNN5602 substation. |
MONDI Štětí |
Installation of electric heating |
2018 |
Paperwork |
Elaboration of project documentation and complete supply and installation of electric pipe heating in several production units, total length of heating pipe ccy ….. Meters. |
Synthos Kralupy |
Temperature regulation in H72ab and H74b reservoirs |
2018 |
Chemistry |
Processing of project documentation and implementation of the part of measurement and regulation, high current and machine modifications during the restoration of automatic temperature control in storage tanks |
MONDI Štětí |
Kaustification Unit Modernization |
2018 |
Paperwork |
Complete provision of work in the instrumentation section on the modernization and expansion of the caustification production unit |
Synthos Kralupa |
Distillation of Butadiene |
2018 |
Chemistry |
Implementation of the electrical and measurement and regulation part during the construction of a new Butadiene Distillation unit, for the purification of incoming Butadiene |
BLIZZARD Beggar |
BLIZZARD Beggar EAME Overhaul Product Center |
2017 |
Construction |
Supply and installation of the MaR part and spatial gas detection during the construction of the first production plant and test area |
MONDI Štětí, as |
MONDI - rewinder - assembly/disassembly work |
2017 |
Paperwork |
Complete assembly work during replacement and reconnection of control systems in operational technology during plant shutdown |
Pivovar Velké Březno |
Heineken Velké Březno - expansion of the premises of the brewery plant |
2017 |
Construction |
Ensuring the complete supply and installation of high-current distribution systems during the expansion of the storage areas of the brewery plant area |
innogy Gas Storage, s.r.o. |
Reconstruction of the PZP Háje lightning rod |
2017 |
Gas industry |
Development of project documentation and implementation of complete reconstruction of lightning conductors on all buildings and probes of the PZP Háje eral |
Net4Gas, s.r.o. |
Modernization of the Kouřim compressor station |
2016 - 2017 |
Gas industry |
Development of implementation project documentation, delivery and installation of the electrical part during the complete modernization of the Kouřim compressor station. |
"DIAMO sp Guard under Ralsk" |
Compressor reconstruction on SLKR I |
2016 - 2017 |
Chemistry and petrochemicals |
Elaboration of implementation project documentation and implementation of the MaR part, including the control system and power current during the installation of the compressor at the acid solution disposal unit |
Lovochemie as |
Universal granulation line |
2016 - 2017 |
Chemistry and petrochemicals |
Implementation of the MaR part during the construction of a new granulation and ammonium nitrate production unit |
KISWIRE CORD CZECH s.r.o. |
Kiswire Reaper |
2016 - 2017 |
Construction |
Delivery and assembly of MaR part incl. control system and spatial gas detection during the construction of the first stage of the production plant |
innogy Gas Storage, s.r.o. |
Reconstruction of PZP Háje lightning conductors |
2017 |
Gas industry |
Development of project documentation and implementation of complete reconstruction of lightning conductors on all buildings and probes of the PZP Háje - Hromosvody area using HVI conductors |
"YARA AB Sweden" |
NITRIC ACID PROJECT 685 MTPD, YARA AB |
2016 |
Chemistry and petrochemicals |
Supply and installation of earthing for construction parts of the newly built nitric acid production unit |
"JSMR Synthetic Rubber ZRT Hungary" |
JSR MOL SYNTHETIC RUBBER ZRT |
2017 |
Chemistry |
Implementation of the measurement and regulation part during the construction of a new unit for the production of synthetic rubber in the Tiszaújváros location |
NOVASPORT |
Reconstruction of BOSSI sander no. 2 |
2017-2018 |
Other |
Elaboration of project documentation, delivery of ex. motors, lights, cable connection, individual and complex tests, commissioning. |
UNIPETROL RPA s.r.o. |
PE3 - OSBL Electrical Part |
2016 - 2019 |
Chemistry |
Supply and installation of LV and HV parts during the construction of a unit for the production of polyethylene, including project documentation - part of OSBL. Supply and installation of HV switchboards, HV transformers, 6kV frequency converters, HV cables, LV switchboards, LV cables, UPS system (5kVA), Diesel aggregate (2500kVA), cable routes. Complete installation of OSBL substation (lighting, emergency lighting, ventilation, air conditioning, EPS, EMS, cameras, attendance system). |
UNIPETROL RPA s.r.o. |
LR 15044 - replacement of FM and 6 kV motors on unit CCR 1392 K02/1,2 |
2016-2018 |
Refineries |
Elaboration of project documentation for building permits, electrical, MaR, HVAC, EPS, mechanical and construction projects. Delivery of 6 kV FM, delivery of 6 kV motors, delivery of new LV switchgear, cable connection. Implementation of a new LV substation. Assembly work, individual and complex tests, commissioning. |
Slovnaft as |
"MOC13/BGHCK/36_FM installation for EM MW103.101B,D,F;MW101.101A " |
2017 |
Chemistry |
Installation of new frequency converters for smooth control of fans. |
Slovnaft as |
ZVZ/MC17/ZVHH/CA/Installation of ultrasonic flowmeters |
2017 |
Chemistry |
Elaboration of project documentation for the installation of new ultrasonic flowmeters for the purpose of automating the filling of tanks. |
Slovnaft as |
Reconstruction of air conditioners in the Slovnaft complex |
2017 |
Chemistry |
Elaboration of project documentation with assessment of heat gains and replacement of existing air conditioners. |
Slovnaft as |
Reconstruction of lighting fixtures in the air compressor room |
2017 |
Chemistry |
Elaboration of project documentation for the installation of new lighting in the compressor room. |
Slovnaft as |
Reconstruction of TS10B substation |
2017 |
Chemistry |
Elaboration of project documentation for the creation of a new TS10B kiosk substation. |
Slovnaft as |
Spare link between HT4 and BS1 |
2017 |
Chemistry |
Elaboration of project documentation for the replacement link of the 6 kV HV dungeon. |
Slovnaft as |
Relocation of signals from bl. 62 (SPF) on bl.51 |
2017 |
Chemistry |
Elaboration of project documentation for relocation of signals from the existing PLC. |
Innogy Gas Storage s.r.o. |
Reconstruction of PZP Háje lightning conductors |
2017 |
Gas industry |
Development of project documentation and implementation of complete reconstruction of lightning conductors on all buildings and probes of the PZP Háje - Hromosvody area using HVI conductors |
BLIZZARD Beggar |
BLIZZARD Beggar EAME Overhaul Product Center |
2017 |
Construction |
Supply and installation of the MaR part and spatial gas detection during the construction of the first production plant and test area |
MONDI Štětí, as |
MONDI - rewinder - assembly/disassembly work |
2017 |
Paperwork |
Complete assembly work during replacement and reconnection of control systems in operational technology during plant shutdown |
Pivovar Velké Březno |
Heineken Velké Březno - expansion of the premises of the brewery plant |
2017 |
Construction |
Ensuring the complete supply and installation of high-current distribution systems during the expansion of the storage areas of the brewery plant area |
innogy Gas Storage, s.r.o. |
Reconstruction of the PZP Háje lightning rod |
2017 |
Gas industry |
Development of project documentation and implementation of complete reconstruction of lightning conductors on all buildings and probes of the PZP Háje eral |
ČEPRO as |
Measuring levels obj 190 and 194 |
2017 |
Chemistry |
Processing of MaR project documentation, supply and replacement of level gauges in objects 190 and 194. Placement of new level gauges and displays and minor mechanical modifications. |
UNIPETROL RPA s.r.o. |
Provision of new ST steam pipe for PE flare |
2017 |
Chemistry |
Processing of project documentation, supply and installation of devices, PLC and SW, including supply of switchboard, cabling, local control boxes and connection of cable routes. |
UNIPETROL RPA s.r.o. |
Automation of K16 washers and blowers on T700 |
2017 |
Chemistry |
Processing of project documentation, delivery and implementation for the replacement of the existing automation of swinging, long-extending blowers and rotary sprinklers (OF-OS) for the K16 boiler, including the replacement of the switchboard, cabling, local controls cabinets and connection of cable routes. New MaR switchboard, fitted with Siemens SIMATIC S7-1500 PLC system. |
NEMAK Czech Republic |
New air conditioning units for offices in AB |
2017 |
Other |
Processing of project implementation documentation, delivery of air conditioning units, electrical connection, individual and complex tests, commissioning |
NEMAK Czech Republic |
Connection of new technology in the new production hall of machining |
2017 |
Other |
Delivery of technical solutions, delivery of cable routes, cabling, connection of new technology, individual tests and complex tests, commissioning |
UNIPETROL RPA s.r.o. / ABB s.r.o. |
Retrofit of HV fields on T 700 |
2017 |
Chemistry |
Delivery and installation of LV superstructures for HV switchgears RWD2 and RWA2, including replacement of measuring transformers, modification of HV fields and cable connection. |
ABB s.r.o. |
R22kV Triangle - substation extension |
2017 |
Other |
Complete assembly of new 10 bays of AVA 22kV switchgear. Dismantling of existing switchboard rpoles and their relocation and connections. |
Unipetrol RPA |
Dosing peroxide on granulation line F1 |
2017 |
Chemistry |
Elaboration of implementation project documentation, complete implementation in the electrical, MaR and mechanical parts. |
ČEPRO as |
Reconstruction of an oily sewer |
2017 |
Chemistry |
Elaboration of implementation project documentation, implementation in the electrical and MaR part. |
Habrinol Děčín |
Control system repair at the PTS factory |
2017 |
Chemistry |
Elaboration of implementation project documentation, repair by replacing the Siemens Simatic control system |
Unipetrol RPA |
Plastic Storage - North |
2017 |
Chemistry |
Elaboration of implementation project documentation, implementation of air engineering, measurement and regulation, electronic fire alarm system |
Habrinol Děčín |
Nitrogen distribution to reactors |
2017 |
Chemistry |
Elaboration of implementation project documentation, implementation in the electrical and MaR part. |
Unipetrol RPA |
Installation of measurements on the ammonia cooling circuit |
2017 |
Chemistry |
Elaboration of implementation project documentation, implementation in the electrical and MaR part. |
Unipetrol RPA |
Replacement of solenoid valves at the ammonia plant |
2017 |
Chemistry |
Elaboration of implementation project documentation, implementation in the electrical and MaR part. |
ČEPRO as |
Reconstruction of the electrical installation of building 234, Hněvice |
2017 |
Refineries |
Material deliveries, assembly and dismantling work, construction work, excavation work, installation of lighting, emergency lighting, processing of documentation of the actual execution of the construction. |
UNIPETROL RPA s.r.o. |
Replacement of DANFOSS frequency converters on st. 9851 |
2017 |
Chemistry |
Delivery and installation of new DANFOSS frequency converters, dismantling of existing equipment and installation of new equipment, setting and parameterization of FM. |
Slovnaft as |
"MOC13/BGHCK/36_Installation of FM for EM MW103.101B,D,F " |
2017 |
Chemistry |
Installation of new frequency converters for smooth control of fans. |
Slovnaft as |
ZVZ/MC17/ZVHH/CA/Installation of ultrasonic flowmeters |
2017 |
Chemistry |
Elaboration of project documentation for the installation of new ultrasonic flowmeters for the purpose of automating the filling of tanks. |
Slovnaft as |
Reconstruction of air conditioning in the Slovnaft area |
2017 |
Chemistry |
Elaboration of project documentation with assessment of heat gains and replacement of existing air conditioners. |
Slovnaft as |
Reconstruction of lighting fixtures in the air compressor room |
2017 |
Chemistry |
Elaboration of project documentation for the installation of new lighting in the compressor room. |
Slovnaft as |
Reconstruction of TS10B substation |
2017 |
Chemistry |
Elaboration of project documentation for the creation of a new TS10B kiosk substation. |
Slovnaft as |
Spare link between HT4 and BS1 |
2017 |
Chemistry |
Elaboration of project documentation for the replacement link of the 6 kV HV dungeon. |
Slovnaft as |
Relocation of signals from bl. 62 (SPF) on bl.51 |
2017 |
Chemistry |
Elaboration of project documentation for relocation of signals from the existing PLC. |
Innogy Gas Storage s.r.o. |
Reconstruction of PZP Háje lightning conductors |
2017 |
Gas industry |
Development of project documentation for the area of PZP Tvrdonice - Hromosvody using HVI conductors |
ČEPS, as |
Reconstruction of the BHD energy complex, buildings E and F |
2016 - 2017 |
Construction |
Complete deliveries and assembly of parts of high-current and low-current distribution systems during the reconstruction of an existing building and the construction of a new building in the premises of ČEPS Prague |
Net4Gas, s.r.o. |
Modernization of the Kouřim compressor station |
2016 - 2017 |
Gas industry |
Development of implementation project documentation, delivery and installation of the electrical part during the complete modernization of the Kouřim compressor station. |
"DIAMO sp Guard under Ralsk" |
Compressor reconstruction on SLKR I |
2016 - 2017 |
Chemistry |
Elaboration of implementation project documentation and implementation of the MaR part, including the control system and power current during the installation of the compressor at the acid solution disposal unit |
Lovochemie as |
Universal granulation line |
2016 - 2017 |
Chemistry |
Implementation of the MaR part during the construction of a new granulation and ammonium nitrate production unit |
KISWIRE CORD CZECH s.r.o. |
Kiswire Reaper |
2016 - 2017 |
Construction |
Delivery and assembly of MaR part incl. control system and spatial gas detection during the construction of the first stage of the production plant |
NOVASPORT |
Reconstruction of BOSSI sander No. 1 |
2016-2017 |
Other |
Elaboration of project documentation, delivery of ex. motors, lights, cable connection, individual and complex tests, commissioning. |
UNIPETROL RPA s.r.o. |
Construction of a new 6.3kV/0.525kV substation at T700 |
2016 - 2017 |
Chemistry |
Construction of a new substation 6.3/0.525kV including project documentation. Delivery of construction works, transformers 6.3/0.525kV, switchboards 525V, lighting and retrofit of HV power arrays. |
LINDE AG |
EJ reconstruction after the fire |
2016 - 2017 |
Chemistry |
Complete dismantling of electrical and MaR equipment affected by the fire (cable routes, cables, equipment), installation of new equipment, cable routes, laying of approx. 500 km of new electrical and MaR cables, equipment connection, revival and tests. |
Innogy Gas Storage s.r.o. |
Reconstruction of PZP Háje lightning conductors |
2017 |
Gas industry |
Development of project documentation and implementation of complete reconstruction of lightning conductors on all buildings and probes of the PZP Háje - Hromosvody area using HVI conductors |
RWE Gas Storage s.r.o. |
Reconstruction of lightning conductors PZP Lobodice |
2016 |
Gas industry |
Development of project documentation and implementation of complete reconstruction of lightning conductors on all buildings and probes of the PZP Lobodice - Hromosvody area using HVI conductors |
UNIPETROL RPA |
Delivery of 17 pieces of valves for OSBL - PE3 |
2016 |
Chemistry |
Delivery of 17 pieces of valves for OSBL including project documentation and technical documentation |
Draslovka Kolín |
Elaboration of wiring diagrams for RIO |
2016 |
Chemistry |
Processing MaR project documentation for train and car turning points |
UNIPETROL RPA |
New LPG route for pyrolysis furnaces |
2016 |
Chemistry |
Processing MaR project documentation, supply and assembly of MaR devices, supply and assembly of ESD HIMA |
RWE Gas Storage s.r.o. |
Reconstruction of lightning conductors PZP Lobodice |
2016 |
Gas industry |
Elaboration of project documentation and implementation of complete reconstruction of lightning conductors on all buildings and probes of the PZP Lobodice eral |
"YARA AB Sweden" |
NITRIC ACID PROJECT 685 MTPD, YARA AB |
2016 |
Chemistry |
Supply and installation of earthing for construction parts of the newly built nitric acid production unit |
UNIPETROL RPA s.r.o. |
PE3 - OSBL Installation |
2016 |
Chemistry |
Supply and installation of LV and HV parts during the construction of a unit for the production of polyethylene |
UNIPETROL RPA |
Replacement of 500V motors in Exd version on EJ |
2016 |
Chemistry |
Processing of implementation project documentation, delivery and assembly of 12 electric motors including power control and signaling cables. Supply and installation of local control cabinets. Connection to the E-tablo supervisory workplace and connection to the HIMA security system at EJ. |
SULTRADE Praha spol. with ro |
Replacement of GA 101A/R and GA 112A/R pumps on EJ |
2016 |
Chemistry |
Processing of implementation project documentation, delivery and installation of new cable routes, delivery and installation of new power, control and signaling cables. Supply and installation of new frequency converters from the manufacturer ABB, construction work and penetrations, supply and installation of new local control cabinets. Connection to the E-tablo supervisory workplace, connection to the HIMA security system. |
UNIPETROL RPA |
Replacement of the ESD HIMA system in the boiler room |
2016 |
Chemistry |
Processing of implementation project documentation, production of new cabinets for the HIMA security system, dismantling of existing switchboards, installation of new switchboards including reconnection of all existing cables, individual and comprehensive testing. |
UNIPETROL RPA |
Expansion of the ESD HIMA system for the new BA 107-110 furnaces |
2016 |
Chemistry |
Processing the implementation project documentation for the expansion of the existing HIMA security system, supply and installation of new switchboards, arming the existing AV 7, 8 switchboards with the new SWESD HIMA. Design and processing by SWESD HIMA. Making cable routes, laying and connecting cables. Individual and comprehensive testing. |
Technip Benelux |
Expansion of the ESD HIMA system for the new BA 101-106 furnaces |
2016 |
Chemistry |
Supply and installation of new switchboards, laying and connection of cables. Individual and comprehensive testing. |
ABB s.r.o. |
Replacement of HV mechanical protection at the substation st. 8401 |
2016 |
Chemistry |
Processing implementation project documentation. The implementation consisted in the reconstruction of 22 HV fields of the existing 6kV switchboard, where HV protection from ABB was installed, the continuous line of the control voltage was replaced, and the complete replacement of the LV superstructure including complete de-wiring. Connection of new HV protection to the MiroScada system, Connection to the E-tablo supervisory workplace. Individual and comprehensive testing. |
Invensys |
Up-grade AW and WP stations, up-grade FBM100 |
2016 |
Chemistry |
Project documentation for implementation, supply of cabling and switchboards, installation of RS cards, commissioning and testing of circuits. Documentation of the actual execution. |
SANDVIK |
Reconstruction of pusher and pusher drives of pilgrims 106 and 109 |
2016 |
Other |
Completion of implementation documentation, delivery of new motors, frequency converters, installation of new power supply and retrofitting of LV switchgear. Equipment tests and commissioning. |
ČESKÁ RAFINERSKÁ, as |
Production of Kerosene JET A1 |
2016 |
Refineries |
Electro and MaR implementation documentation processing, supply assurance, modification of HV switchgear, supply of new LV switchgear, new cable routes + cable distributions, MaR supply of field instrumentation devices (RV, Level gauges , pressure and temperature converters...) connection to the existing ØS fy. Foxboro. Supply of HW and SW of the existing Foxboro ŘS. |
ČESKÁ RAFINERSKÁ, as |
CCR Unit Reliability Increase |
2016 |
Refineries |
Ensuring deliveries, modification of LV switchboards, delivery of new LV switchboards, new cable routes + cable distributions. Tests, commissioning. |
ČESKÁ RAFINERSKÁ, as |
Increasing pump reliability P1310-P02/1 |
2016 |
Refineries |
Processing of implementation project documentation electrical + MaR. Delivery of a new 6kV motor to an EX environment. Modification of the HV switchboard, SW modification of the DCS system, tests, recovery. |
ČESKÁ RAFINERSKÁ, as |
LR 13034 Ensuring the operability of the road terminal in Jiřetín |
2016 |
Refineries |
Modernization of the road terminal in Jiřetín, part of MaR and electrical. Replacement of the existing MFX tank truck filling control system with the FCM II system from Toptech Systems, Inc. Replacement of SIMATIC S5 safety PLC with S7. SW modifications in the COTAS system and the mentioned systems. Replaced all wiring, junction boxes and thermometers on the pouring arms. Modifications in the new technical room and substation. Introducing new equipment to the market (specified meters) according to the MID in cooperation with the ČMI. |
ČESKÁ RAFINERSKÁ, as |
LR 14059 -WET STOCK LOSSES/EXCISE TAX DUTY EQUIPMENT. Measurement of inflows and outflows of liquid products from tax warehouses of Česká rafinérská Litvínov |
2016 |
Refineries |
Delivery and installation of 34 measuring sets of specified gauges (mass flow meter, thermometer and pressure gauge), including introduction to the market according to MID. SW modifications of existing DCS and PLC. |
UNIPETROL RPA s.r.o. |
PE3 - OSBL Basic Design and Detail Design |
2015 - 2016 |
Chemistry |
Elaboration of project documentation for the electrical part (LV and HV) for a new polyethylene production unit |
UNIPETROL RPA s.r.o. |
Ethylene Unit Reconstruction |
2015 - 2015 |
Chemistry |
Delivery and installation of electrical parts, ASŘTP, GDS and FDS during the complete reconstruction of the ethylene unit |
Česká rafinérrská as |
Road Terminal Jiřetín |
2015-2016 |
Chemistry |
Replacement of the control system for the Jiřetín road fuel dispensing terminal |
Plzenská teplárenská, as |
ZEVO Chotíkov |
2015-2016 |
Energy |
Supply and installation of HV and LV electricity and parts of ASŘTP for the construction of a new energy source and municipal waste incinerator in Pilsen |
RWE Gas Storage s.r.o. |
Measurement of pressures in the annulus of probes |
2016 |
Gas industry |
Implementation of the electrical and MaR profession for measuring pressures in the annulus of injection and production probes on the underground gas reservoirs of Dolní Dunajovice and Tvrdonice with a total number of approx. 150. |
RWE Gas Storage s.r.o. |
Measurement of pressures in the annulus of probes |
2015 |
Gas industry |
Processing of implementation project documentation for measuring pressures in the annulus of injection and production probes on the underground gas reservoirs of Dolní Dunajovice and Tvrdonice with a total number of approx. 150. |
Skota Auto, as |
Gas regulation station |
2015 |
Gas industry |
Implementation of the electrical and MaR part incl. ŘS at the newly built VTL natural gas regulation station at the Kvasiny plant |
UNIPETROL RPA s.r.o. |
Reconstruction of AZ 6kV switchgear leads |
2015 |
Water Management |
Processing of electrical and control system project documentation, supply and installation of new AZ cabinet equipment including new control system and operator panel. Implementation of settings and tests including commissioning. |
UNIPETROL RPA, s.r.o. |
Replacing A620 Air Condensers on NTS |
2015 |
Chemistry |
MaR project documentation processing, supply and installation of electrical and MaR, supply and installation of ESD HIMA, supervisory workplace, HVAC. |
UNIPETROL RPA, s.r.o. |
Change of use of the 2nd floor of building 2837 for VŠCHT |
2015 |
Chemistry |
Processing of electrical project documentation, structured cabling, low currents, air conditioning, supply and installation of electrical, structured cabling, low current installations, air conditioning. |
SANDVIK |
Ventilation of halls 4 and 5 |
2015 |
Other |
Delivery and installation of electrical + HVAC, tests, equipment commissioning. |
ČESKÁ RAFINERSKÁ, as |
LR 14015 - New optical connection of FARs 4 and 5 |
2015 |
Refineries |
Processing project documentation in the MaR section. Supply, assembly, fiberization and connection of optical cables for communication between the ŘS. |
UNIPETROL RPA |
Measuring on the order of raw water |
2015 |
Chemistry |
Processing of implementation project documentation for electrical and MaR and ŘS parts, supply and installation of power and control and signaling cables, supply and installation of cable routes, supply and installation of flow meters (specified gauges ), processing of application SW for control and monitoring. |
BIS Czech s.r.o. |
Implementation of measures to shut down the steam order 0.7MPa |
2015 |
Chemistry |
Supply and installation of switchboards, cables and routes. Arming of existing switchboards. Supply and installation of field instrumentation devices. Connection of existing technology to the new ŘS. Setup, testing and commissioning of equipment. |
UNIPETROL RPA |
Contact Sludge Pumps |
2015 |
Energy |
Realization project documentation, supply and installation of cabling, cards for ŘS and switchboards. Commissioning and handing over the work. |
UNIPETROL RPA |
Measuring fire water on PCH |
2015 |
Chemistry |
Processing of implementation project documentation for electrical and MaR and ŘS parts, supply and installation of power and control and signaling cables, supply and installation of cable routes, supply and installation of flow meters, processing of application SW for control and monitoring. |
ČKD DIZ |
Replacement of P 912A,B pumps at NTS |
2015 |
Chemistry |
UNIPETROL RPA |
Sewage segregation from storm drains |
2015 |
Chemistry |
Supplies and installations of cabling and switchboards. Enabling wireless communication. Project documentation. Delivery of the work. |
ČEPRO as |
Reconstruction of the electrical installation of building 232, Hněvice |
2015 |
Refineries |
Material deliveries, assembly and dismantling work, construction work, excavation work, installation of lighting, emergency lighting, processing of documentation of the actual execution of the construction. |
UNIPETROL RPA |
ØS for gas burners on T700 |
2015-2016 |
Energy |
Realization project documentation, supply and assembly of PLC and field instrumentation devices, supply and assembly of cabling, SW work, commissioning, tests, handover of work. |
SIEMENS |
Reconstruction of switchboards MR 22, 23, 24 |
2015-2016 |
Chemistry |
Reconstruction of switchboards MR 22, 23, 24. Each switchboard consists of 5 fields. The reconstruction consisted of the replacement of existing circuit breakers with new ones, including the modification of pastures, the laying of cables, the replacement of switchboard doors, including the installation of new devices. Parameterization and setting of circuit breakers. Connection to the E-tablo supervisory workplace. Individual and comprehensive testing, including testing of automatic failures. |
UNIPETROL RPA |
EC-801 Air Condenser Replacement |
2015-2016 |
Chemistry |
Processing of implementation project documentation, implementation including, in particular, arming of switchboards, supply of FM, installation of cable routes, supply and installation of power and control cables, addition of ŘS, production of fire protection seals, supply of local control boxes. |
UNIPETROL RPA, s.r.o. |
C5 Fraction Inhibitor Dosing Optimization |
2014 |
Chemistry |
Supply and installation of field instrumentation devices, valves, cables and routes. Arming of existing switchboards. Setup, testing and commissioning of equipment. |
UNIPETROL RPA, s.r.o. |
LPG bottling |
2014 |
Chemistry |
Processing project documentation in the electrical section. Supply and installation of new LV switchboards, arming and switching of switchboards, supply and installation of cables, supply and installation of cable routes, supply and installation of Ex switchboards, construction of grounding, supply and installation of lighting. |
CC PLAST, s.r.o. |
Performance Boost |
2014 |
Other |
Supply and installation of switchboard and power cable to enhance the performance of existing technology. |
ČEPRO as |
Reconstruction of the electrical installation of building 231, Hněvice |
2014 |
Energy |
Arming of switchboards, supply and installation of cables, supply and installation of cable routes, supply and installation of lighting, supply and installation of emergency lighting, supply and installation of switchboards for Ex, construction work, excavations, construction of cable routes, adjustment of AUMA valves. |
UNIPETROL RPA, s.r.o. |
DCS deployment at the PCH water plant |
2014 |
Chemistry |
Supply and installation of switchboards, DeltaV control systems, cables and routes. Arming of existing switchboards. Connection of existing technology to the new ŘS. Setup, testing and commissioning of equipment. |
UNIPETROL RPA s.r.o. |
TG 12 Overhaul |
2014 |
Energy |
Processing of electrical and mechanical project documentation, delivery and installation of new coolers, delivery and installation of new protections including adjustments to the LDS ŘS, settings, testing and commissioning. |
UNIPETROL RPA, s.r.o. |
Control of compressor rooms st. 1532 and st. 1535 from the control room st.1424 |
2014 |
Chemistry |
Supply and installation of field instrumentation devices, valves, switchboards, ŘS Foxboro, cables and routes. Arming of existing switchboards. Connection of existing technology to the new ŘS. Setup, testing and commissioning of equipment. |
LDS Sever, spol. with ro |
Fix data collection R6_7 WWTP |
2014 |
Energy |
Supply and installation of Simatic control systems, switchboards, cabling and connections. Setup, testing and commissioning of equipment. |
Draslovka as |
TMA bottling and storage |
2014 |
Chemistry |
Supply and installation of field instrumentation devices, valves, switchboards, DeltaV control systems, cables and routes. Arming of existing switchboards. Connection of existing technology to the new ŘS. Setup, testing and commissioning of equipment. |
SYNTHOS Kralupy as |
Modification of the existing Benzene bottling station - II.stage |
2014 |
Chemistry |
Processing of project documentation in the electrical part, arming of switchboards, supply and installation of cables, supply and installation of cable routes, supply and installation of switchboards to Ex. |
Pardubice Hospital |
HV substation 35kV |
2014 |
Other |
Delivery and installation of HV substation 35kV + cable termination, commissioning. |
LIAZ s.r.o. model house |
Delivery of hot runner control system for Ford mold |
2014 |
Industry |
Processing of electrical and syst project documentation, technical design of injection control, supply of HW, processing and SW, supply and installation of switchboard, supply and installation of cables. |
ČEPRO as |
Reconstruction of the electrical installation of building 231, Hněvice |
2014 |
Refineries |
Material deliveries, assembly and dismantling work, construction work, excavation work, installation of lighting, emergency lighting, processing of documentation of the actual execution of the construction. |
UNIPETROL RPA |
New PLC for WWTP |
2014 |
Chemistry |
Material deliveries, assembly and disassembly work, processing of documentation for the actual construction. |
UNIPETROL RPA |
LPG bottling on track 234b |
2014 |
Chemistry |
Processing of implementation project documentation for electrical and MaR and ŘS parts, supply and installation of power and control and signaling cables, supply and installation of cable routes, supply and installation of Ex lighting and Ex controllers, reconstruction of the existing LV substation, processing of application SW for control and monitoring. |
UNIPETROL RPA |
Replacement of compressor room cable routes |
2014 |
Chemistry |
Design of a technical solution for the replacement of existing cable routes, including the processing of detailed project documentation. Part of the implementation was the replacement of the existing cable routes on which the cables were installed. |
VVV Most s.r.o. |
Replacement of T700 coaling electric motors |
2014 |
Chemistry |
Processing implementation project documentation, arming switchboards, laying and connecting power and control cables. |
ČESKÁ RAFINERSKÁ, as |
Ventilation of the corridors of tank station D |
2014-2015 |
Refineries |
Processing electrical + HVAC project documentation, supply and installation of high current + HVAC, tests, commissioning. |
RSF Elekltronik |
Connecting all technology |
2014-2015 |
Other |
Electrical project processing, delivery and assembly, tests, technology commissioning. |
ČESKÁ RAFINERSKÁ, as |
LR 14037 - Supply and installation of security ramp |
2014-2015 |
Refinery - filler |
Processing project documentation in the electrical and MaR section. Delivery and installation of a safety ramp for railway tanks, adjustments in the Simatic system, blockage of the movement of tanks. |
SYNTHOS Kralupy as |
Reconstruction of TR237 |
2014-2015 |
Energy |
Processing electrical project documentation, delivery of switchgear 6kV - ZS1. |
"ČEZ, as Severočeské doly, as" |
Modernization of sorted coal loading |
2014 - 2015 |
Mining Industry |
Complete implementation of part of high-current distributions incl. new substations, measurement and regulation incl. ŘS and low-current distribution systems during the modernization and expansion of the loading of sorted coal in the Bílina locality |
RWE Gas Storage s.r.o. |
Emergency depressurization of the technological equipment of PZP Dolní Dunajovice |
2014 - 2015 |
Gas industry |
Delivery, installation of measurement and regulation and high-current distribution to ensure increased safety of gas storage technology. |
"Synthos Dwory 7 Sp. z o. o Poland" |
Construction of a new butadiene production unit |
2014 - 2015 |
Chemistry |
Implementation of the measurement and regulation part during the construction of a new unit for the production of synthetic rubber in the Oświęcim location |
Lovochemie as |
Modernization of calcium salt production |
2014 |
Chemistry |
Supply and installation of HV, LV and measurement and regulation electrical parts for the modernization of the existing and the construction of a new calcium salt production unit |
RWE Gas Storage s.r.o. |
Modernization of Solar Taurus 70 turbines |
2014 |
Gas industry |
Assembly work of measurement and regulation and parts of high current during the modernization of the control systems of gas turbines on the underground gas storage |
MONDI Štětí, as |
PM6 Line Edit |
2014 |
Paperwork |
Project documentation and implementation of the electrical, measurement and regulation part including the control system during the modernization of the PM6 paper machine |
RSF Elektronik spol. with ro |
Production area RSF Stříbro |
2014 |
Construction |
Project documentation and implementation of the electrical and measurement and regulation part for the newly built production plant in Stříbra |
RWE Energo, s.r.o. |
Modifications in the Teplárny Náchod substation |
2014 |
Energy |
Ensuring the performance of dismantling work and subsequent modifications in substation R 0.5kV-section A, B, C in Teplárna Náchod |
Net4Gas, s.r.o. |
Modifications of the KS Hostim pipe yard |
2014 |
Gas industry |
Reconstruction of the entrance and exit objects of the Hostim compressor station to a new route closure. Delivery of telemetry and IT cells, provision of power supply, HV connections and substation and LV power supply, realization of the MaR part incl. control system, connection to the N4G dispatching and implementation of security systems |
SYNTHOS Kralupy as |
Modification of the existing Benzene bottling station - II.stage |
2014 |
Chemistry and petrochemicals |
Processing of project documentation in the electrical part, arming of switchboards, supply and installation of cables, supply and installation of cable routes, supply and installation of switchboards to Ex. |
SYNTHOS Kralupy as |
Reconstruction of TR237 |
2014-2015 |
Energy |
Processing electrical project documentation, delivery of switchgear 6kV - ZS1. |
"Synthos Dwory 7 Sp. z o. o Poland" |
Construction of a new butadiene production unit |
2014 - 2015 |
Chemistry and petrochemicals |
Implementation of the measurement and regulation part during the construction of a new unit for the production of synthetic rubber in the Oświęcim location |
Lovochemie as |
Modernization of calcium salt production |
2014 |
Chemistry and petrochemicals |
Supply and installation of HV, LV and measurement and regulation electrical parts for the modernization of the existing and the construction of a new calcium salt production unit |
RWE Gas Storage s.r.o. |
Modernization of Solar Taurus 70 turbines |
2014 |
Gas industry |
Assembly work of measurement and regulation and parts of high current during the modernization of the control systems of gas turbines on the underground gas storage |
MONDI Štětí, as |
PM6 Line Edit |
2014 |
Paperwork |
Project documentation and implementation of the electrical, measurement and regulation part including the control system during the modernization of the PM6 paper machine |
RWE Energo, s.r.o. |
Modifications in the Teplárny Náchod substation |
2014 |
Energy |
Ensuring the performance of dismantling work and subsequent modifications in substation R 0.5kV-section A, B, C in Teplárna Náchod |
Net4Gas, s.r.o. |
Modifications of the KS Hostim pipe yard |
2014 |
Gas industry |
Reconstruction of the entrance and exit objects of the Hostim compressor station to a new route closure. Delivery of telemetry and IT cells, provision of power supply, HV connections and substation and LV power supply, realization of the MaR part incl. control system, connection to the N4G dispatching and implementation of security systems |
RWE Gas Storage s.r.o. |
Connecting the control unit to PZP Háje |
2013 - 2014 |
Gas industry |
Supply and installation of MaR and electrical parts for connecting the control unit for controlling probe closures on the Háje underground gas storage tank |
JSP International s.r.o., Cheb |
Heating p-Tanks |
2013 - 2014 |
Chemistry and petrochemicals |
Elaboration of implementation project documentation, supply and installation of electric heating and management of reservoirs during plastic processing |
Lovochemie as |
Clean technologies |
2013 |
Energy |
Electrical assembly work during the reconstruction of exchange and transfer stations in the investor's premises during the modernization of heating facilities. |
"DIAMO sp Guard under Ralsk" |
Compressor reconstruction on SLKR I |
2013 |
Chemistry and petrochemicals |
Elaboration of implementation project documentation and implementation of the MaR part, including the control system and power current during the installation of the compressor at the acid solution disposal unit |
RWE Gas Storage s.r.o. |
Compressor installation at PZP Lobodice |
2013 |
Gas industry |
Delivery and installation of electrical parts incl. HV and measurement and regulation equipment during the installation of a new compressor on the gas reservoir |
Doosan Bobcat Engineering Ltd |
Research and Development Center |
2013 - 2014 |
Construction |
Processing of project documentation, delivery and assembly of the MaR part including the control system and SW processing |
RWE Gas Storage s.r.o. |
Connecting the control unit to PZP Háje |
2013 - 2014 |
Gas industry |
Supply and installation of MaR and electrical parts for connecting the control unit for controlling probe closures on the Háje underground gas storage tank |
JSP International s.r.o., Cheb |
P-TANK HEATING |
2013 -2014 |
Chemistry |
Realization project documentation, supply and installation of electric heating and storage management during plastics processing |
UNIPETROL RPA, s.r.o. |
ZKR 255 A6 screw compressor control reconstruction |
2013 |
Chemistry |
Delivery of implementation project documentation. Delivery, installation and commissioning of diagnostics and PLC Simatic series S7-300 for 10 compressors. |
ČESKÁ RAFINERSKÁ, as |
V. Registry |
2013 |
Chemistry |
Manage the Asset Register. |
UNIPETROL RPA, s.r.o. |
Reconstruction of PCH heating - protective cabinets |
2013 |
Petrochemicals |
Delivery of implementation project documentation. Delivery of 73 protective boxes for field instrumentation. |
UNIPETROL RPA, s.r.o. |
MP Farrel Bearing Cooling Repair |
2013 |
Chemistry |
Delivery of implementation project documentation. Delivery, installation and commissioning of field instrumentation devices. SW modifications in PLC SIMATIC. Delivery of machine parts. |
UNIPETROL RPA, s.r.o. |
Disposal of off-gases from storage tanks FB 103 and 901 |
2013 |
Petrochemicals |
Supply, installation and commissioning of field instrumentation devices. Supply of I/O cards for DCS ABB. |
ČESKÁ RAFINERSKÁ, as |
New air conditioning units on CRC 3411 |
2013 |
Chemistry |
Implementation project documentation of electricity, supply and installation of LV, tests, commissioning. |
AIR PRODUCTS |
"Electrical and Instrumentation Construction Work for Air Products Project EN-11-2936, AGC Teplice Project" |
2013 |
Chemistry |
Realization project documentation of lighting, grounding of oxygen and nitrogen production technology for AGC technology. Supply and assembly of electrical and MaR equipment. |
UNIPETROL RPA, s.r.o. |
FM for water plant pumps on PCH |
2013 |
Water Management |
RPD, supply and installation of 6kV FM, HV protection and equipment, cabling, routes, new FM substation, lighting, HVAC, grounding, 6kV switchgear, etc. Supply and installation of ŘS for FM. Setup, testing and commissioning of equipment. |
C-Energy Wild |
Reconstruction of 110kV cable and T102 transformer |
2013 |
Energy |
Supply and installation of transformers 110/10.5/6.3kV; 65/65/25MW. |
UNIPETROL RPA, s.r.o. |
Reconstruction of electric heating STAGE II |
2013 |
Chemistry |
Technical assistance in the implementation of the order. Realization of MaR protective cabinets including electric heating, supply of power switchboards, supply of specific material for the given project. |
UNIPETROL RPA, s.r.o. |
FM for water plant 230 |
2013 |
Water management |
RPD, supply and installation of 6kV FM, HV protection and equipment, cabling, routes, new FM substation, lighting, HVAC, grounding, 6kV switchgear, etc. Supply and installation of ŘS for FM. Setup, testing and commissioning of equipment. |
UNIPETROL RPA, s.r.o. |
PCHI Power Fuse Retrofit |
2013 |
Chemistry |
Replacement of the power protection of LV switchboards including all devices in the switchboard, connection to the electrical supervision workplace. |
Spolana as |
Vn cable routing for Caprolactam plant |
2013 |
Chemistry |
Supply and installation of a new cable route including 6kV cable and control cables. |
UNIPETROL RPA, s.r.o. |
EJ compressor room lighting reconstruction |
2013 |
Chemistry |
Realization project documentation for compressor room lighting, supply and installation of EEx - LED lighting including cable routes and power cables. |
UNIPETROL RPA, s.r.o. |
Replacement of EJ compressor room cable routes |
2013 |
Chemistry |
Supply and installation of new cable routes, dismantling of existing routes, handling of cables. |
UNIPETROL RPA, s.r.o. |
Frequency converters for pumps P-211 on ZM |
2013 |
Chemistry |
RPD, supply and installation of FM 525V, switchboards, retrofitting of existing switchboards, supply and installation of motors for pumps, controllers, cables and routes, grounding, etc. Modifications of RS. Setup, testing and commissioning of equipment. |
UNIPETROL RPA, s.r.o. |
RS for PCH water plant |
2013 |
Water Management |
Supply and installation of transformers, UPS, switchboards, cables and routes. Arming of existing switchboards. Connection of existing technology to the new ŘS. Setup, testing and commissioning of equipment. |
OHL ŽS as |
Plzen - Slovany Sports Hall |
2013 |
Other |
High-current electrical installation HV, LV, tests and commissioning. |
UNIPETROL RPA, s.r.o. |
Retrofit of MR70 switchboard power assurance on EJ |
2013 |
Chemistry |
Replacement of the power protection of LV switchboards including all devices in the switchboard, connection to the electrical supervision workplace. |
UNIPETROL RPA, s.r.o. |
Disposal of off-gases from the reservoir FB 103,901 |
2013 |
Chemistry |
Arming of switchboards, supply and installation of cables, supply and installation of switchboards for Ex, supply and installation of electric heating. |
UNIPETROL RPA, s.r.o. |
Reconstruction of CHV st. 0425 |
2013 |
Water Management |
Supply and installation of compensation, controllers, cables, routes, lighting, grounding and lightning rods. Retooling of existing switchboards, etc. Connection and extension of the existing ŘS, sensing of taps, etc. Setting, testing and commissioning of equipment. |
Cepro |
Reconstruction of electrical installation of substation 235 Slad Hněvice |
2013 |
Energy |
Arming of switchboards, supply and installation of cables, supply and installation of switchboards for Ex, construction work, excavations, making cable routes, setting AUMA valves. |
PKN Orlen |
PEC BA 108 - PLOCK Poland |
2013 |
Chemistry |
Processing of project documentation, supply and installation of FM including settings, making cable routes, supply and installation of electric heating switchboard in an environment with a risk of explosion. |
DoorHan s.r.o. |
SWIETELSKY - Hall DoorHan Kadaň |
2013 |
Other |
High current electrical installation, EPS. |
ČESKÁ RAFINERSKÁ, as |
OR 03003 Balance measurement |
2013 |
Refineries |
Replacement of obsolete 17 pcs of volumetric flow meters with new mass flow meters. Complete delivery incl. RPD part of MaR, electrical and mechanical. |
PKN Orlen |
Plock - oven |
2013 |
Petrochemicals |
Delivery and installation of MaR and electrical equipment for modifications to the existing furnace, including RPD MaR and electrical. |
EURO SUPPORT |
EUROSUPPORT camera system |
2013 |
Chemistry |
Complete supply and installation of a camera system (72 cameras) including RPD. |
RWE Gas Storage s.r.o. |
Compressor installation at PZP Lobodice |
2013 |
Gas industry |
Delivery and installation of electrical parts incl. HV and measurement and regulation equipment during the installation of a new compressor on the gas storage tank. |
SULTRADE Praha s.r.o. |
TBK diagnostic system |
2013 |
Chemistry |
Processing of implementation project documentation, arming of switchboards, delivery and installation of cables, delivery and installation of cable routes, delivery and installation of switchboards to Ex. |
Lovochemie as |
Clean technologies |
2013 |
Energy |
Electrical assembly work during the reconstruction of exchange and transfer stations in the investor's premises during the modernization of heating facilities. |
UNIPETROL RPA, s.r.o. |
Adjustment of GB-201 gas compressor interstage cooling |
2013 |
Chemistry |
Supply and installation of field instrumentation devices, valves, cables and routes. Arming of existing switchboards. Setup, testing and commissioning of equipment. |
Doosan |
New production hall |
2013-2014 |
Other |
Delivery and installation of high-voltage, low-voltage, high-current distribution, testing, commissioning. |
UNIPETROL RPA, s.r.o. |
LDS Substation Reconstruction - R200 - Part II B3 - |
2013-2015 |
Energy |
Supply and installation of 6kV equipment for R200 substation dungeons. Dismantling old dungeons. Supply and installation of HV, protection, etc. Installation of HV switches, disconnectors, isolators, 6kV cables, LV cables and bus system. Setup, testing and commissioning of equipment. |
RSF Elektronik |
New AB, production halls, storage hall |
2013-2015 |
Other |
Processing of high-current, low-current projects and complete delivery and assembly of HV, LV, MaR, low-current, EPS, CCTV, setting, revival, tests. |
RWE Gas Storage s.r.o. |
Compressor installation at PZP Lobodice |
2013 |
Gas industry |
Delivery and installation of electrical parts incl. HV and measurement and regulation equipment during the installation of a new compressor on the gas reservoir |
"DIAMO sp Guard under Ralsk" |
Compressor reconstruction on SLKR I |
2013 |
Chemistry |
Elaboration of implementation project documentation and implementation of the MaR part, including the control system and power current during the installation of the compressor at the acid solution disposal unit |
Lovochemie as |
Clean technologies |
2013 |
Energy |
Electrical assembly work during the reconstruction of the extraction and transfer stations in the investor's premises during the modernization of the heating of the buildings |
RWE Gas Storage s.r.o. |
Compressor installation at PZP Lobodice |
2013 |
Gas industry |
Delivery and installation of electrical parts incl. HV and measurement and regulation equipment during the installation of a new compressor on the gas reservoir |
Lovochemie as |
Ammonia bottling control room reconstruction |
2012 - 2013 |
Chemistry |
Elaboration of implementation project documentation and implementation of the reconstruction of the ammonia control room, including power supply switching and management of ammonia bottling technology. The contract includes construction work and mechanical modifications to the ammonia distribution pipeline |
SOKOLOVSKÁ UHELNÁ, as |
Backup dryer power supply |
2012 - 2013 |
Energy |
Processing of project documentation for a building permit completed to the level of an implementation project to ensure replacement power supply for operation of the dryer |
Net4Gas, s.r.o. |
Building 6180 – Brumovice II |
2012 - 2013 |
Gas industry |
Elaboration of implementation project documentation and implementation of construction, mechanical and electrical activities during the reconstruction of pipeline technology and modernization of ŘS TU05S Uherčice, PS012 Uherčice, PS010 Hrušky |
RWE Gas Storage s.r.o. |
Tvrdonice border reinforcement |
2012 |
Gas industry |
Supply and installation of SŘTP for new safety fittings used for emergency closure, including supply and installation of field instrumentation and cabling and connection to the storage tank ŘS |
Lovochemie as |
Construction of spherical ammonia tanks |
2012 - 2013 |
Chemistry |
Delivery and installation of electrical parts incl. production of switchboards, MaR parts incl. RS SIMATIC and signaling of the presence of ammonia during the construction of two above-ground ammonia storage tanks |
Lovochemie as |
Ammonia bottling control room reconstruction |
2012 - 2013 |
Chemistry and petrochemicals |
Elaboration of implementation project documentation and implementation of the reconstruction of the ammonia control room, including power supply switching and management of ammonia bottling technology. The contract includes construction work and mechanical modifications to the ammonia distribution pipeline |
Net4Gas, s.r.o. |
Building 6180 – Brumovice II |
2012 - 2013 |
Gas industry |
Elaboration of implementation project documentation and implementation of construction, mechanical and electrical activities during the reconstruction of pipeline technology and modernization of ŘS TU05S Uherčice, PS012 Uherčice, PS010 Hrušky |
RWE Gas Storage s.r.o. |
Tvrdonice border reinforcement |
2012 |
Gas industry |
Supply and installation of SŘTP for new safety fittings used for emergency closure, including supply and installation of field instrumentation and cabling and connection to the storage tank ŘS |
Lovochemie as |
Construction of spherical ammonia tanks |
2012 - 2013 |
Chemistry and petrochemicals |
Delivery and installation of electrical parts incl. production of switchboards, MaR parts incl. RS SIMATIC and signaling of the presence of ammonia during the construction of two above-ground ammonia storage tanks |
"OAO NAK AZOT Novomoskovsk Russia " |
Construction of an ammonium nitrate production unit |
2012 |
Chemistry and petrochemicals |
Complete development of implementation project documentation of the MaR part and management system respecting GOST standards for a new ammonium nitrate production unit |
"OAO NAK AZOT Novomoskovsk Russia " |
Construction of an ammonium nitrate production unit |
2012 |
Chemistry |
Complete development of implementation project documentation of the MaR part and management system respecting GOST standards for a new ammonium nitrate production unit |
Net4Gas, s.r.o. |
Connection KS Břeclav and PZP Tvrdonice |
2011 - 2012 |
Gas industry |
Project documentation, supply and installation of part of high-current distribution and MaR incl. of the control system during the construction of the gas pipeline connection between the compressor station and the underground gas storage |
"DIAMO sp Guard under Ralsk" |
Neutralization and decontamination station - NDS10 |
2011 - 2012 |
Chemistry |
Delivery and assembly of MaR part incl. a complete management system solution during the construction of a new unit for the processing of mother liquors |
"PGNiG SA Warsaw Poland" |
Underground gas storage and combined cycle power plant |
2011 - 2012 |
Gas industry |
Delivery and installation of the MaR part as part of the construction of an underground gas storage tank and a new steam-gas power plant |
"DIAMO sp Guard under Ralsk" |
Neutralization and decontamination station - NDS10 |
2011 - 2012 |
Chemistry |
Delivery and installation as part of the expansion of the existing HV substation 35kV during the construction of a new unit for the processing of mother liquors |
"OAO Čerepovec Russia" |
Urea Production Plant |
2011 - 2012 |
Chemistry |
Delivery of assembly material for the MaR part and delivery of gas detection incl. chief assembly and commissioning for the management of the technology for the production of carbamide with a capacity of 1500 tons/day |
Net4Gas, s.r.o. |
Gazela pipeline |
2011 - 2012 |
Gas industry |
Supply and installation of heavy-duty distribution systems, including the production of switchboards for the construction of the new Brandov border transfer station and other route closures on the gas pipeline |
Lovochemie as |
Reverse osmosis connection to CVD DHW |
2011 |
Energy |
Project documentation, delivery and installation of a new control system incl. SW creation and involvement in the central production dispatch |
Town of Varnsdorf |
Swimming pool reconstruction and completion |
2010-2011 |
Construction |
Delivery and installation of the MaR part including the control system |
Česká rafinérská, as |
Reconstruction of the ventilation of the tank yard corridors |
2010-2011 |
Petrochemicals |
Processing of project documentation and implementation of the construction part, HVAC part, electrical and MaR part during the construction of two engine and electrical rooms, including measurement and regulation |
"SYNTHOS PBR s.r.o. Kralupy nad Vltavou" |
"Polybutadiene UNIT Electrical part " |
2010-2011 |
Chemistry |
Complete implementation of part of the operational electrical distribution during the construction of the new production unit Polybutadiene UNIT |
Česká rafinérská as |
PLC and FM replacement at CRC construction site |
2010-2011 |
Petrochemicals |
Electrical and MaR implementation project documentation including PLC for device control, delivery and assembly, Realization during operation of the entire unit |
Net4Gas, s.r.o. |
Connection KS Břeclav and PZP Tvrdonice |
2011 - 2012 |
Gas industry |
Project documentation, supply and installation of part of high-current distribution and MaR incl. of the control system during the construction of the gas pipeline connection between the compressor station and the underground gas storage |
"DIAMO sp Guard under Ralsk" |
Neutralization and decontamination station - NDS10 |
2011 - 2012 |
Chemistry and petrochemicals |
Delivery and assembly of MaR part incl. a complete management system solution during the construction of a new unit for the processing of mother liquors |
"PGNiG SA Warsaw Poland" |
Underground gas storage and combined cycle power plant |
2011 - 2012 |
Gas industry |
Delivery and installation of the MaR part as part of the construction of an underground gas storage tank and a new steam-gas power plant |
"DIAMO sp Guard under Ralsk" |
Neutralization and decontamination station - NDS10 |
2011 - 2012 |
Chemistry and petrochemicals |
Delivery and installation as part of the expansion of the existing HV substation 35kV during the construction of a new unit for the processing of mother liquors |
Net4Gas, s.r.o. |
Gazela pipeline |
2011 - 2012 |
Gas industry |
Supply and installation of heavy-duty distribution systems, including the production of switchboards for the construction of the new Brandov border transfer station and other route closures on the gas pipeline |
SYNTHOS Kralupy as |
"Polybutadiene UNIT Electrical part " |
2010-2011 |
Chemistry and petrochemicals |
Complete implementation of part of the operational electrical distribution during the construction of the new production unit Polybutadiene UNIT |
"BORSODCHEM - KAZINCBARCIKA Hungary" |
Nitric acid production unit |
2010 |
Chemistry and petrochemicals |
Implementation of part of the SŘTP at the newly built nitric acid production unit with a capacity of 660 tons/day |
VIA Distribution |
Repair of substation wiring |
2010 |
Energy |
Project documentation, deliveries and electrical installation during the complete reconstruction of the Jih substation in Chomutov |
"BORSODCHEM - KAZINCBARCIKA Hungary" |
Nitric acid production unit |
2010 |
Chemistry |
Implementation of part of the SŘTP at the newly built nitric acid production unit with a capacity of 660 tons/day |
UNITED ENERGY as |
New engine room lighting |
2010 |
Energy |
Delivery and installation incl. processing of the actual design during the complete replacement of the existing lighting of the small and large machine room in UE Komořany, including the supply of power switchboards |
WEBA Olomouc as |
WEBA Olomouc Production Plant |
2010 |
Construction |
Complete supply and installation of high-current electrical installation incl. HV 22kV substations and switchgears, low currents and MaR for the new production plant in Olomouc. |
AGC Flat Glass Czech |
Hall 3C lighting |
2010 |
Construction |
Complete supply and installation of high-current electrical installation in the new hall and chemical warehouse in the premises of the production plant in Teplice |
Energo Vidonice s.r.o. |
FPE Vidonice |
2010 |
Energy |
Processing of implementation project documentation, processing permits, supply and installation of electrical, HV and LV equipment and monitoring system for a new ground-based PV plant |
Česká rafinérská as |
Modernization of EPS and camera system |
2010 |
Petrochemicals |
Complete replacement of the electronic fire alarm during the reconstruction of the security system of the Kralupa nad Vltavou chemical production complex |
ETC International s.r.o. |
FVE Doksana |
2010 |
Energy |
Processing of implementation project documentation, processing permits, supply and installation of electrical, HV and LV equipment and monitoring system for a new ground-based PV plant |
ACTHERM SERVIS as |
Reconstruction of substation control R22.0 |
2010 |
Energy |
Processing implementation project documentation delivery and installation of the Simatic control system during substation reconstruction |
ČESKÁ RAFINÉRSKÁ as |
SKP security system |
2010 |
Petrochemicals |
Processing of implementation project documentation, delivery and installation of a perimeter system for building security, delivery and installation of a camera system and connection to PCO |
UNIPETROL RPA s.r.o. |
Oxygen analyzers in CHC plant silos |
2010 |
Chemistry |
Implementation documentation, supply of analyzers for O2 determination including switchboards, sample treatment, control system for successive measurement of samples and pumps for sampling |
Lovochemie as |
Limestone Mill Reconstruction |
2010 |
Chemistry |
Delivery and installation of electrical and MaR parts including connection to the control system as part of the reconstruction of the limestone mill |
"DIAMO sp Guard under Ralsk" |
Modernization of the VROD control system |
2010 |
Chemistry |
Project documentation, delivery and installation of equipment during the modernization of the ŘS technology VROD (high-temperature reduction of nitrogen oxides). Allen Bradley |
SOKOLOVSKÁ UHELNÁ, as |
PPC Power Reconstruction |
2010 |
Energy |
Design, production and installation of power switchboards for steam-gas cycle generators, including replacement of the control system |